West Basin Municipal Water District
CA

Staff Report

JMMCRWRP Phase II Expansion (MBR Equipment Procurement, CIP-10022) Amendment

Information

Department:EngineeringSponsors:
Category:Report

Attachments

  1. Printout
  2. Site Map

Body

Fiscal Impact:

Funds for the 2.0 MGD tMBR treatment system project are included in the Fiscal Year 2017-18 Capital Improvements Project Budget.  However, the costs for the new tMBR are being capitalized and will be paid back through a fixed-charge by Andeavor, which also includes a capital contribution by CalWater to lower Andeavor’s overall cost.

 

Environmental Compliance:

Not applicable.

 

Committee History:

This item was not reviewed by a Committee.

Meeting History

Jan 4, 2018 10:15 AM  Board of Directors Special
RESULT:APPROVED [UNANIMOUS]
MOVER:Donald L. Dear, Treasurer
SECONDER:Carol W. Kwan, Member
AYES:Harold C. Williams, Scott Houston, Donald L. Dear, Gloria D. Gray, Carol W. Kwan